Chocolate Path River Wall Stabilisation
Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Purpose:
This report seeks approval to commission
contractors and undertake the construction and asset maintenance
works of the 'Chocolate Path'.
Decision:
Cabinet:
1. Approved the spend for the remainder of the approved budget to undertake the (4.42m) full stabilisation works required for the complete extent of the Chocolate Path Wall.
2. Noted that the structural condition of the whole river wall continues to get worse and that there remains an urgent need for the full amount of funding sought (4.42m), for full repair and stabilisation of Chocolate Path throughout.
3. Delegated to the Executive Director Growth and Regeneration, in consultation with the Cabinet Member for Transport and Connectivity, the authority to procure contractors to carry out all works identified in Appendix A.
Report author: Peter Mann
Publication date: 04/09/2018
Date of decision: 04/09/2018
Decided at meeting: 04/09/2018 - Cabinet
Effective from: 12/09/2018
Accompanying Documents:
- Final Chocolate Path decision pathway paper - 4 September 2018 PDF 131 KB
- Appendix D - Risk Register Assessment PDF 51 KB
- Appendix E - Chocolate Path - Equality Relevance Check PM Signed PDF 162 KB
- 4A Chocolate Path Appendix F - Eco Impact Checklist PDF 78 KB
- Appendix M - Chocolate Path Condition Photos and Location Plan PDF 2 MB
- Appendix N - Jacobs Managment Report PDF 9 MB