Decision details

COVID 19 – Cross Directorate Application for Contract Awards, Extensions and Variations Necessary due to the Impact of COVID 19 on Commissioning and Procurement Activity.

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To seek approval to adopt an approach to Contract Awards, Extensions and Variations Necessary due to the impact of COVID 19 on Commissioning and Procurement Activity.

Decision:

Cabinet:

  1. Authorised the Executive Director Growth and Regeneration, in consultation with Cabinet Member for Housing, for the purposes of mitigating COVID 19, to take all appropriate steps:

(a)   to extend existing contracts, and award new contract(s), in-line with the procurement routes outlined in Appendix A, and;

(b)   to make any further necessary extensions/variations to all such contracts.

  1. Authorised the Executive Director People, in consultation with the Cabinet Member Adult Social Care, for the purposes of mitigating COVID 19, to take all appropriate steps:

(a)   to extend existing contracts, and award new contract(s) in-line with the procurement routes outlined in Appendix A, and

(b)   to make any further necessary extensions/variations to all such contracts;

 

3.      Authorised the Executive Director of Growth and Regeneration to vary and allocate the grant award of £1,077,100.00 MHCLG funding for 20/21 (Rough Sleeping Services Grant).

Report author: Jacqui Jensen

Publication date: 02/06/2020

Date of decision: 02/06/2020

Decided at meeting: 02/06/2020 - Cabinet

Effective from: 12/06/2020