Bristol Beacon - Construction Contract Deed of Variation
Decision Maker: Executive Director: Growth and Regeneration
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
The Bristol Beacon Transformation project has
faced significant challenges due to unforeseen issues with the
building structure and Covid-19. To secure completion of the
project, Cabinet approved an increase in budget from £52.9m
to £106.9m in March 2021. The project requires a Deed of
Variation to amend the construction contract and reflect the
increased budget and transfer of design responsibilities and risk
that has been negotiated with the contracting partner.
The Councils Strategic Partner has conducted due diligence and
submitted a report recommending that the Deed of Variation meets
the objectives set out in the decision at Cabinet. The Bristol
Music Trust have also been consulted and are content for the
document to be sealed. There is agreement between Bristol Music
Trust and the Council that the Collaboration Agreement will need to
be revised in due course to align with the Deed of Variation.
Decision:
On the 9th of March, the Cabinet made the
following decision:
Cabinet Authorised the Executive Director for Growth
a) Enter contracts for professional services required to complete
the project;
b) Amend the construction contract to transfer risk and secure
greater cost and programme certainty;
c) Agree any new/additional terms of grant with any grant funding
bodies.
In line with the decision taken at Cabinet on 9th March 2021. The
project requires the Executive Director for Growth
Alternative options considered:
Option 1 - Re-tender and secure a new
contractor
oTime implications would have a catastrophic effect on project
delivery
oSoft market discussion suggested that there would be very little
interest in bidding from alternative contractors and any bids would
likely be significantly more than approved budget
Option 2 -
Option 3 -
Publication date: 12/04/2021
Date of decision: 09/04/2021