Temple Island – Strategic Partner - August to November 2021
Decision Maker: Executive Director: Growth and Regeneration
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
BCC have competitively tendered rates with the
Strategic Partner and have secured the resource needed from the
Partnership.
Call off from professional services contract with Strategic Partner
(Arcadis working with Arup and Mott MacDonald) towards Temple
Island Enabling Works.
Decision:
Temple Island enabling works project is a
5-year programme of design and construction for a series of
enabling works, to facilitate development of the Temple Island
site.
In October 2020 Cabinet authorised the Executive Director for
Growth and Regeneration, in consultation with the Mayor, the S.151
Officer, and Director of Legal Services to use up to £32m of
repurposed EDF funding towards the enabling works.
This decision utilises £420,000 of the £32m funding
allocation to procure the Council’s Strategic Capital
Partnership for a period of 4 months to provide project management,
cost management and design services to maintain progress.
Alternative options considered:
Option 1 - Comparison has been done against
similar professional services contract. The Strategic Partner offer
best value for money under the competitively procured Partnership
arrangement and fees are within the project budget.
Option 2 -
Option 3 -
Publication date: 13/10/2021
Date of decision: 13/10/2021