Modern.gov Breadcrumb
- Decision details
Modern.gov Content
Decision details
BSH/HRA Mould and mechanical ventilation works
Decision Maker: Executive Director: Growth and Regeneration
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
This provided the quickest and most efficient
route to market to provide resources for mould and mechanical
ventilation works considering the delays in procuring the new
Responsive Repairs Framework.
Decision:
Approval to award a temporary arrangement for
a provider to carry out mould and mechanical ventilation works to
Housing owned occupied properties while a permanent contract is
procured. Due to the delay in procuring the new Responsive Repairs
framework, a backlog of mould and mechanical ventilation works has
developed. This temporary arrangement will ensure BCC fulfils its
statutory duty to fulfil repairs and will help avoid potential
disrepair cases.
Alternative options considered:
Option 1 - None
Option 2 -
Option 3 -
Publication date: 26/09/2022
Date of decision: 05/08/2022