Extension to Asbestos Surveying contract,
Decision Maker: Executive Director: Growth and Regeneration
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
The Undertaking of Refurbishment and
Demolition plus targeted and Full Asbestos Management Surveys
contract was due to end at the end of February 2023. However, the
contractor is performing to a high standard and BCC are receiving a
good service so we are extending the contract for the full 24 month
option.
As the contract is going well and the option is available, this is
the most suitable course of action for the service and avoids
needing to go through another competitive tender process which
takes time and would also have a considerable cost to BCC.
Decision:
To extend the Asbestos Surveying contract for
24 months to 1 March 2025.
Alternative options considered:
Option 1 - The alternative was to go through
another competitive tender process, but due to the reasons above
the option to extend was taken.
Option 2 -
Option 3 -
Publication date: 02/02/2023
Date of decision: 02/02/2023