Decision Maker: Executive Director: Growth and Regeneration
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
The project’s overall budget of
£32m includes for the Riverwall repairs works. This is
required as part of the works needed to enable Temple Island for
development. This project is funded by the EDF funding from WECA,
secured in 2020. A PRF has been obtained from Procurement and Legal
on this expenditure.
Approval to enter into a contract with CCSL as
Principal Contractor to undertake the riverwall repair works at
Temple Island as part of the Temple Island Enabling Works
project.
Option 1 - A competitive open market ITT was
launched in December 2022. From the responses submitted, the panel
judged and scored the responses (captured in Award Report attached)
and determined that CCSL were the winning bid. Therefore, the
project wish to engage their services through an NEC4 Option A
contract. The alternatives are: to reject the tender bids and
postpone this works to next summer or not complete them at all. The
former would result in difficulty on site to accommodate a repairs
contractor whilst the remediation works are scheduled, the latter
would mean we cannot fulfil our obligations to future developer
LandG. Therefore we propose this to be the best route to procuring
a Principal Contractor to complete the repairs.
Option 2 -
Option 3 -
Publication date: 10/03/2023
Date of decision: 03/03/2023