WECA Green Recovery Fund – Easiform Pilot
Decision Maker: Executive Director: Growth and Regeneration
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
In January 2022, a funding bid was submitted
to WECA for £500k – along with two other housing
providers in the region (Curo and Brighter Places).
The bid is to support a scheme to retrofit 25 Bristol City Council
properties using the whole-house retrofit approach to PAS 2035,
which provides guaranteed performance and comfort for tenants and a
real energy cost saving.
The funding is made up as follows:
o£200,000 confirmed grant from the European Regional
Development Fund (ERDF)
o£300,000 from the Combined Authority’s Green Recovery
Fund,
The application for funding of £500k under the Innovative
Housing Retrofit Scheme has been awarded from the Green Recovery
Fund Grant.
Due to the value of the funding and need to enter into agreements
and in order to deliver the grant funded outcomes, an Officer
Executive Decision will be required now that the application is
successful.
The purpose of this is to make the Cabinet Member with
responsibility for Housing aware of a grant funding opportunity and
to seek agreement to be part of an approved funding
application.
Decision:
To accept a grant of £500k from the WECA
Green Recovery Fund to be used on the Easiform pilot being
delivered by Ameresco and managed by Specialist project Team which
will retrofit 25 Bristol City Council properties using the
whole-house retrofit approach to PAS 2035, which provides
guaranteed performance and comfort for tenants and a real energy
cost saving.
Alternative options considered:
Option 1 - There were no other options,
because The Housing Investment Programme detailed all the
investment plans for Bristol City Council.
Option 2 -
Option 3 -
Publication date: 20/03/2023
Date of decision: 17/03/2023