Refurbishment and upgrade of low-rise blocks at Vincent Close.

Decision Maker: Executive Director: Growth and Regeneration

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

To maintain our stock to safe standard and to meet current legislation

Decision:

Approval to award a contract to carry out refurbishment work at Vincent Close. To secure the services of an architect to design the refurbishment and upgrade of 4 no low-rise blocks at Vincent Close.

Alternative options considered:

Option 1 - There are no other options as the properties require these works to ensure they are safe. The contract was therefore procured with Procurement and Legal input to ensure correct process followed.
Option 2 -
Option 3 -

Publication date: 11/09/2023

Date of decision: 07/09/2023