Highway improvement works to A4 Access Road ‘Plot 12’ as part of the scope of the Temple Island Enabling Works.
Decision Maker: Director: Property, Assets and Infrastructure
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
The Council must undertake these road
improvement works to ensure that the access road can be used for
emergency access to Temple Island when the future development comes
forward. This package forms part of the Enabling Works Condition
under the Development Agreement with Legal and General. The budget
for these works has been included in the WECA EDF funding
agreement. The proposed procurement route is award to Colas Ltd via
a Call off from CCS Framework Lot 1.2.2: Civil Engineering Works
and Minor Associated Building Works and Services–South
England. The call-off mechanism used is a Direct Award
procedure.
Decision:
The works are road re-surfacing, local
rebuilding of parts of the road that have failed, kerb replacement,
fence replacement, edge protection and signage and road markings on
the A4 Access Road that runs down to Temple Island. It is one of
the packages of Enabling Works required to be undertaken under the
Development Agreement with Legal and General.
Alternative options considered:
Option 1 - This is an appropriate framework
because the works were originally scheduled for completion summer
2023 and all four contractors on the BCC Highways Lot 5 framework
were approached and declined citing the low rates and unacceptable
Indexation clause. The works must be completed by end of October
2023 and therefore if a call-off tendering exercise was used, it
would take 6-8 weeks from launch to award, whereas the project
requires these works to commence on site in 6 weeks. Therefore as
this is urgent and time restricted, the project do not have time to
run a call-off tendering exercise and require to go directly to
Colas.
Option 2 -
Option 3 -
Publication date: 11/09/2023
Date of decision: 07/09/2023