Modern.gov Breadcrumb
- Decision details
Modern.gov Content
Decision details
East Bristol Liveable Neighbourhoods, Trial scheme installation
Decision Maker: Executive Director: Growth and Regeneration
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
Following a tender process via the
Council’s Highways Framework, the first phase of the East
Bristol Liveable Neighbourhood scheme is due to be installed during
the autumn of 2024.
This officer decision notice is in relation to awarding the
contract to the successful contractor, ETM ltd with a bid of
£473,862.64.
A previous delegated decision on 4 April 2023 authorised the
Executive Director for Growth and Regeneration, in consultation
with the Committee Chair and the S151 officer to take all steps
required to procure and award all necessary contracts up to the
value of £1.371m (including any individual contracts over
£0.500m) to deliver the scheme, which this 473k sits
under
Decision:
To approve the tender report to commence the
construction of the trial East Bristol Liveable Neighbourhood
project.
Alternative options considered:
Option 1 - The only alterative option would be
not awarding the contract, but this would mean the project would be
abandoned and the 6 million pounds capital funding for the project
would be lost. There is a risk we would also have to give back
capital funding we have spent to date which would put a financial
pressure on the council.
Publication date: 26/09/2024
Date of decision: 03/09/2024