Decision details
A4 Portway Strategic Corridor – Phase 2 Kerb Realignment and Footway Improvement
Decision Maker: Executive Director: Growth and Regeneration
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Purpose:
As set out in the Committee on 6 February
2025, the A4 Portway Strategic Corridor project is a scheme looking
to make highway infrastructure improvements on the A4 Portway that
prioritise sustainable transport. In order to deliver these
changes, the Council needs to secure the support of a civil
engineering delivery partner. This Officer Decision Notice follows
on from the decision 3 (iii) of item 12 at the 6 February 2025
Transport and Connectivity Committee, in seeking to award a
contract to a civil construction company from Lot 6 of the Bristol
Highways Framework for the delivery of Phase 2 of the A4 Portway
Strategic Corridor, the kerb realignment and footway
improvements.
Decision:
Exercising the delegated approvals granted in
the February 2025 Committee paper, that the S151 Officer, Executive
Director of Growth and Regeneration, and Chair of the Transport and
Connectivity Committee approve
(i)The tender process undertaken through Lot 6 of the Bristol
Highways Asset Management and Associated Works Framework to procure
a civils contractor to deliver the Phase 2 of the A4 Portway
Strategic Corridor, kerb realignment and footway
construction.
(ii)The awarding of the civils contract to the winning bid from the
tender run under Lot 6 of the Bristol Highways Framework in the
value of £1,465,292.47
Alternative options considered:
Option 1 - Within the Full Business Case
submitted to Bristol City Council Transport and Connectivity
Committee in February 2025 was a section outlining the options
considered for the project (section 2.11 of the FBC) highlighting
the reasons why options were discounted and why the preferred
option was carried forward. The Full Business Case can be seen in
the appendices submitted alongside the Committee Report.
Publication date: 09/04/2025
Date of decision: 08/04/2025
Effective from: 18/04/2025