Decision details
Housing Revenue Account (HRA) Development Perfect Circle Architectural Fees Compensation Event
Decision Maker: Executive Director: Growth and Regeneration
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
To accelerate the provision of housing to meet
the Mayors target of building 2000 homes a year – 800
affordable a year by 2020.
Decision:
Perfect Circle have been appointed to project
manage the delivery of Bonnington, Kingswear and Florence Brown HRA
New build developments – from feasibility through to the
construction of new homes. Perfect Circles original appointment
included a Provisional Sum for architectural fees. The fee proposal
from the selected architectural practice is above the provisional
sum allowance within Perfect Circles Contracted Sum.
Alternative options considered:
Option 1 - An alternative option to procuring
Perfect Circle would be to procure an architectural practice
separately however this would add significant time to the overall
delivery programme.
Option 2 -
Option 3 -
Publication date: 14/06/2019
Date of decision: 12/06/2019