Decision details

Cumberland Road Stabilisation Project

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Decision:

1. Cabinet approved implementing the construction and delivery of Option 2 set out in the report - full design to stabilise all elements of the project (which will also include full mitigation measures to ensure further resilience).

2. Cabinet approved the additional Capital funding estimation of £4,023,190 funded from underspends in the 19/20 capital programme.

3. Cabinet approved additional flood protection measures to raise the wall to 2065 flood protection requirements as an integral part of the detailed stabilisation design.

4. Cabinet authorised the Executive Director for Growth and Regeneration to enter into a contract for the above works to implement Option 2.

Report author: Colin Molton

Publication date: 01/10/2019

Date of decision: 01/10/2019

Decided at meeting: 01/10/2019 - Cabinet

Effective from: 09/10/2019