Unlocking Lockleaze – acceptance of £6.686m HIF funding award from Homes England
Decision Maker: Executive Director: Growth and Regeneration
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
To accept external funding contract in
accordance with Cabinet decision of 6th March 2018.
Decision:
In accordance with Cabinet decisions of 6th
March 2018 to accept and invest a £6.686m Housing
Infrastructure Fund (HIF) award to support housing delivery and
regeneration in Lockleaze, a decision is now made to enter into
contract with Homes England to accept this £6.686m
award.
Alternative options considered:
Option 1 - Contract conditions have been
considered and are in accordance with Cabinet decisions and
delivery objectives.
Option 2 -
Option 3 -
Publication date: 11/11/2019
Date of decision: 11/11/2019