To note an urgent officer key decision taken
by the Executive Director Growth and Regeneration on 31 March 2022
in relation to electricity contract procurement and
renewals.
1. Noted the urgent key decision taken by the Executive Director Growth and Regeneration on 31 March 2022 to:
a) procure an 18-month flexible electricity contract via a compliant public sector framework (LASER) covering streetlights and supplies to smaller buildings (called “non-half-hourly”) at a cost of £12m and
b) extend the half hourly buildings contract to cover the transition to new arrangement by two months at a cost of £1.5m.
2. Noted that the Energy Service will tender for Sleeving for the council’s larger buildings, in line with previously delegated authority given by Cabinet in February 2021.
Report author: Steve Ransom