Sleeved Power Purchase Agreement for Half-Hourly (large) electricity supplies.

Decision Maker: Executive Director: Growth and Regeneration

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

•This arrangement covers around a third of total BCC electricity demand
•The new arrangements will significantly reduce BCC exposure to market prices for electricity, and will provide a supply of zero-carbon electricity.
•The current supply contracts expired on 31st July 2022, meaning that the Council is now incurring significantly more expensive off-contract rates for electricity.
•There is a clear and pressing need to maintain a compliant contract for power to supply council buildings.

Decision:

Contract award for Sleeved Power Purchase for half-hourly (large) electricity supplies from August 2022 to September 2023. Consultation has taken place with the relevant Cabinet Member..

Alternative options considered:

Option 1 - Extending the previous supply contract by a further period would have delayed the benefits of sleeving and would also have incurred significant additional cost.
A standard contract renewal process would forego the cost and carbon benefits of sleeving.
Option 2 -
Option 3 -

Publication date: 15/08/2022

Date of decision: 12/08/2022