BSH/HRA Responsive Repairs Backlog – Round 2
Decision Maker: Executive Director: Growth and Regeneration
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
This provided the quickest and most efficient
route to market to reduce the backlog of repairs currently
outstanding which is considerably impacting the service provided to
the homes of tenants across the city.
Decision:
Approval to award a further temporary
arrangement for a provider to carry out responsive repairs to
Housing owned properties while a permanent contract is procured.
This is to assist with the reduction of the still considerable RR
backlog which has occurred as a result of the Covid-19 pandemic and
the subsequent impact on internal and external resources. The
contract was a direct award to an incumbent supplier based on the
lack of bids from other suppliers on the tender, and the urgent
requirement for additional resources to reduce the backlog.
Alternative options considered:
Option 1 - None
Option 2 -
Option 3 -
Publication date: 26/09/2022
Date of decision: 15/06/2022