Modern.gov Breadcrumb
- Issue
Modern.gov Content
Issue details
Heat Pump Ready Project, Veritherm contract award
•To enable the delivery of the project in
accordance with the Cabinet Decision of 7 February 2023 to accept
the funding and deliver this project.
From our market research and consultation with industry experts
Veritherm are the only company able to have the technical
capability and capacity to offer a combination of home survey tools
as required. We estimate that their combined offer provides a
discount of at approximately 65%.
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 29/03/2023
Decision due: 7 Mar 2023 by Director: Economy of Place
Lead member: Councillor Kye Dudd cllr.kye.dudd@bristol.gov.uk
Contact: Louise Baker, Executive Support Manager Email: louise.baker@bristol.gov.uk.
Decisions
- 29/03/2023 - Heat Pump Ready Project, Veritherm contract award