South Bristol Liveable Neighbourhoods Project – Funding for business case
On 23 January 2024, Cabinet approved decision
to accept £600k in CRSTS funding from WECA.
Original commission under the Bristol City Council-Strategic
Partnership Initiative with contract value of circa £72k for
Phase 1 (feasibility study) of the SBLN Project was completed in
March 2024.
The decision is to approve additional funding for development of
the draft Full Business Case and preliminary designs by April
2025.
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 08/07/2024
Decision due: 1 Jul 2024 by Executive Director: Growth and Regeneration
Lead member: Councillor Ed Plowden Cllr.Ed.Plowden@bristol.gov.uk
Contact: John Smith, Executive Director: Growth & Regeneration Email: john.smith2@bristol.gov.uk.