East Bristol Liveable Neighbourhoods, Trial scheme installation
Following a tender process via the
Council’s Highways Framework, the first phase of the East
Bristol Liveable Neighbourhood scheme is due to be installed during
the autumn of 2024.
This officer decision notice is in relation to awarding the
contract to the successful contractor, ETM ltd with a bid of
£473,862.64.
A previous delegated decision on 4 April 2023 authorised the
Executive Director for Growth and Regeneration, in consultation
with the Committee Chair and the S151 officer to take all steps
required to procure and award all necessary contracts up to the
value of £1.371m (including any individual contracts over
£0.500m) to deliver the scheme, which this 473k sits
under
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 26/09/2024
Decision due: 3 Sep 2024 by Executive Director: Growth and Regeneration
Lead member: Councillor Ed Plowden Cllr.Ed.Plowden@bristol.gov.uk
Contact: John Smith, Executive Director: Growth & Regeneration Email: john.smith2@bristol.gov.uk.