Modern.gov Breadcrumb

Modern.gov Content

Decision details

Kingsweston Lane Footbridge

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To update Cabinet on the successful revised planning decision for Kingsweston Lane footbridge and to seek approval to proceed with the project and spend the required capital funding as set out in the budget.

Decision:

That cabinet:

1.      Approved the commencement of the refurbishment works on Kingweston Lane Footbridge in accordance with the Planning Permission and Listed Building Consent and as outlined in this report noting the project will be initiated in late 2023 with an estimated completion date of December 2024 subject to contractor availability.

2.      Authorised the Executive Director Growth and Regeneration in consultation with the mayor to take all steps required to procure and award the contract(s) necessary for the implementation of this project in-line with the procurement routes and maximum budget envelopes outlined in this report.

3.      Authorised the Executive Director for Growth and Regeneration in consultation with the mayor, to invoke any subsequent extensions/variations or amendments specifically defined in the contract(s) being awarded, up to the maximum budget envelope outlined in this report.

Report author: Shaun Taylor

Publication date: 06/06/2023

Date of decision: 06/06/2023

Decided at meeting: 06/06/2023 - Cabinet

Effective from: 14/06/2023

Accompanying Documents: