St Bernadette’s Rugby Club - Stage 1 Contract Award for detailed design stage for a new rugby clubhouse and playing pitches at Whitehouse Centre, Fulford Road
Decision Maker: Executive Director: Growth and Regeneration
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
On 7th May 2019 (agenda item 15):
“Cabinet authorised the Executive Director, Growth and
Regeneration in consultation with the Cabinet Member for Housing to
procure multi-disciplinary design teams to submit detailed planning
applications of new facilities for St Bernadette’s Rugby Club
and the 21st (Gladstone) Scout Group”. Further to this
decision, and discontinuation of the previous contract for the
works, the scope of the project has been value-engineered and the
project budget increased in order to proceed with this contract
– decision taken by Executive Director, Growth
Decision:
Enter into a contract with Stepnell Ltd. for
Stage 1 Contract for the redevelopment of the Whitehouse Centre,
Fulford Road, for rugby clubhouse and playing pitches, including
the detailed design stage and submission of a planning application
for revised scheme.
Alternative options considered:
Option 1 - The procurement of a contractor
through a further competition via the Procure Partnership Framework
South West was undertaken, however the highest scoring contractor
did not wish to proceed with the contract, and the other tender
submissions were above budget.
Option 2 -
Option 3 -