Scheme Approval Report for the development of land at St Peters (`Land-led’ scheme).
Decision Maker: Executive Director: Growth and Regeneration
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
This decision is made in accordance with The
Project 1000 Affordable Housing Delivery Plan 2022-25 and outlines
how the council will focus its land, time, money, and influence to
improve the way affordable housing is delivered in Bristol.
The council’s ambition is to work with partners, local
communities and developers to deliver
1000 new affordable homes each year by 2024.
To develop this plan, we have reviewed the successes and challenges
of previous housing projects in Bristol. We will use these
experiences to determine how we can support the affordable homes
that the city needs.
Decision:
Award of a contract to Stepnell Construction
Ltd for the construction of 28 new council homes, A Community
Centre and BCC run Childrens Home. Consultation has taken place
with the Section 151 Officer, Cabinet Member for Finance,
Governance and Performance and Cabinet Member for Housing Delivery
and Homes.
Alternative options considered:
Option 1 - The alternative is to sell the
sites, but this is likely to result in a lower level of
“genuinely affordable” homes being delivered.
Option 2 - The scheme enables the HRA to spend RTB receipts at risk
of being returned.
Option 3 -The proposal is for a revenue generating scheme that will
benefit the HRA Business Plan.
Publication date: 01/09/2022
Date of decision: 30/08/2022