BSH/HRA Flooring Works
Decision Maker: Executive Director: Growth and Regeneration
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
This provided the quickest and most efficient
route to market to provide resources for flooring works to occupied
and void properties considering the delays in procuring the new
Responsive Repairs Framework.
Decision:
Approval to award a temporary arrangement for
a provider to carry out flooring works to Housing owned occupied
properties while a permanent contract is procured. Due to the delay
in procuring the new Responsive Repairs framework, there are no
longer any resources for providing flooring works to occupied and
void properties. This temporary arrangement will ensure BCC fulfils
its statutory duty to fulfil repairs.
Alternative options considered:
Option 1 - None
Option 2 -
Option 3 -
Publication date: 26/09/2022
Date of decision: 19/08/2022