Technical services pursuant to managing the Bedminster Green civils works contract
Decision Maker: Executive Director: Growth and Regeneration
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
The services procured will assist Bristol City
Council in managing this civils works contract, which is of
considerable size and complexity. There is currently insufficient
resource to manage this contract using internal members of staff.
Bristol City Council is satisfied that the resource procured
externally has the relevant skills and expertise to fulfil the
role.
Decision:
The director for Growth and Regeneration has
approved the procurement of NEC4 Project management services and
Site supervision services during the ongoing civils contract for
the highway improvement works package at Bedminster Green, which
comprises works around Malago Road and Whitehouse Lane. The
decision follows a tender process under the West of England
Professional Services Framework.
Alternative options considered:
Option 1 - Using an agency organisation to
appoint specific individual people was considered, however this
commission instead uses a consultancy organisation to fulfil the
roles of NEC4 (New Engineering Contract) Site Supervisor and NEC4
Project Manager at all times using any means necessary, and to
match any resource demands and technical expertise required to
complete the project. Appointing individuals through an agency
would leave BCC exposed to risk of resource insufficiency due to
staff absence / departure or unforeseen increases in project
complexity/resource demands, and Bristol City Council would also
need to fulfil specialist back-office functions such as Quantity
Surveying, which are all covered under the tendered contract.
Option 2 -
Option 3 -
Publication date: 02/12/2022
Date of decision: 24/11/2022