Decision details

Scheme Approval Report for the development of land at Greville, Lacey Road, Stockwood (`Land-led’ scheme).

Decision Maker: Executive Director: Growth and Regeneration

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

Project 1000 Affordable Housing Delivery Plan, and New Council Homes Development Programme (HRA Business Plan)
This decision is made in accordance with The Project 1000 Affordable Housing Delivery Plan 2022-25 which outlines how the council will focus its land, time, money, and influence to improve the way affordable housing is delivered in Bristol.
This decision is also in accordance with the New Council Homes Development Programme (HRA Business Plan) approved by Cabinet and Full Council.

Decision:

That the Executive Director of Growth and Regeneration in consultation with the Mayor (with appropriate legal, finance and procurement advice) approves entering into contract with Stepnell Ltd. for the construction of 21 new council homes and 5 Shared ownership homes, with a start on site in August 2024.

Alternative options considered:

Option 1 - The alternative is to sell the sites, but this is likely to result in a lower level of “genuinely affordable” homes being delivered
Option 2 - The proposal is for a revenue generating scheme that will benefit the HRA Business Plan.

Publication date: 10/04/2024

Date of decision: 10/04/2024