Hengrove Park Perfect Circle Contract – Supplementary Workpackage
Decision Maker: Director: Development of Place
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
Bristol City Council entered into a contract
with Perfect Circle to provide multi-disciplinary consultancy
services to submit an Outline Planning Application with design
codes for Hengrove Park. The application was taken to Development
Control Committee on 27th February 2019 and refused by the
Committee. Following discussions with the Cabinet Member for
Housing, the Council will resubmit a new Outline Planning
Application for Hengrove Park responding to the reasons for
refusal.
Decision:
Appoint Perfect Circle to submit a new Outline
Planning Application with Design Codes for Hengrove Park, under the
Council’s existing contract with Perfect Circle as a
Supplementary Workpackage.
Alternative options considered:
Option 1 -
No other options were considered. The Council has an existing
contract with Perfect Circle. No other organisations are in a
position to complete the work.
Option 2 -
Option 3 -
Publication date: 30/04/2019
Date of decision: 30/04/2019