Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Purpose:
To seek approval of the Building Practice
Capital Budget allocation of a proposed capital spend of 11 million
across a number of sites and work types.
Decision:
Cabinet:
- Approved the Building Practice
Capital Programme 2022-2026 at appendix A into the Council’s
Capital Programme – with the projects due to commence in
2022/23 into the Approved Programme for delivery and projects due
in later years into the Development Pool.
- Authorised the Executive Director
Resources in consultation with the Cabinet Member and Deputy Mayor
– Finance, Governance and Performance to take all steps
required (including procuring and awarding contracts over
£500k) to undertake the works identified at Appendix A at a
cost of up to £11m.
- Noted the intention to bring the
programme back to Cabinet each year with an updated programme of
works.
Report author: John Walsh
Publication date: 05/04/2022
Date of decision: 05/04/2022
Decided at meeting: 05/04/2022 - Cabinet
Effective from: 13/04/2022
Accompanying Documents: