Project Leadership – Project 1000

Decision Maker: Executive Director: Growth and Regeneration

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

Experienced leadership capacity is required to ensure successful delivery of the Temporary Accommodation Transformation Project, one of the of the Council’s top priorities. The Council needs to procure this resource as there is no existing internal capacity. Arcadis have already been procured to meet this type of need and facilitate high pace of delivery.

Decision:

To commission the Strategic Partner (Arcadis) to support the Temporary Accommodation Transformation Project by arrangement of a consultant Programme Director and Programme Managers.

Alternative options considered:

Option 1 - Internal resource is not available
Option 2 - Procurement of resource from open market or other framework discounted because of time required and cost of process being unfavourable in comparison to pre procured Arcadis
Option 3 -

Publication date: 15/05/2023

Date of decision: 11/05/2023