Structural refurbishment works to Bath Old Bridge
Decision Maker: Executive Director: Growth and Regeneration
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
Works has already commenced on this Project
using DFT challenge funding awarded in 2018/19. The works is
currently on site and the allocated funding of £166k is now
fully committed. The intention of the use of this allocated funding
was to commence the works in 2018/19. The intention is the
continuation of the structural refurbishment works using Capital
funding from the Transportation Capital Budget allocated in
2019/20.
Decision:
To continue with the refurbishment works on
Bath Old Bridge which commenced on site in 2018/19, using Capital
Budgets for 2019/20.
Alternative options considered:
Option 1 -
Alternative option would be to cancel which would be of detriment
of the authority undertaking its statutory duty and would cost the
authority more in the long term therefore rejected.
Option 2 -
Option 3 -
Publication date: 15/04/2019
Date of decision: 10/04/2019