Issue - meetings
Cumberland Road Stabilisation Project
Meeting: 01/10/2019 - Cabinet (Item 17.)
17. Cumberland Road Stabilisation Project PDF 157 KB
Additional documents:
- Appendix A - Business Case - Chocolate Path Wall Repairs - Rev A, item 17. PDF 659 KB
- Appendix D - Risk Register Assessment, item 17. PDF 51 KB
- Appendix E - Chocolate Path Stabilisation_EQIA Relevance Check - July 2019, item 17. PDF 373 KB
- Appendix F - ECO Impact Checklist - Rev A, item 17. PDF 110 KB
- Exempt App I - Cumberland Road Final , View reasons restricted (17./6)
- Appendix M - Chocolate Path Condition Photos and Location Plan, item 17. PDF 2 MB
- Appendix N - Jacobs Managment Report, item 17. PDF 9 MB
Decision:
1. Cabinet approved implementing the construction and delivery of Option 2 set out in the report - full design to stabilise all elements of the project (which will also include full mitigation measures to ensure further resilience).
2. Cabinet approved the additional Capital funding estimation of £4,023,190 funded from underspends in the 19/20 capital programme.
3. Cabinet approved additional flood protection measures to raise the wall to 2065 flood protection requirements as an integral part of the detailed stabilisation design.
4. Cabinet authorised the Executive Director for Growth and Regeneration to enter into a contract for the above works to implement Option 2.