That Cabinet:

1.     Approved the revised scope of the Capricorn Quay project as outlined in this report.

2.     Authorised the Executive Director for Growth and Regeneration, in consultation with the Mayor, to take all steps to accept and spend £480,000 of WECA funding to install floating eco-systems around new pontoons at Capricorn Quay.

3.     Authorised the Executive Director for Growth and Regeneration, in consultation with the Mayor, to make further applications to WECA’s Green Infrastructure Fund for funding of eco system projects in the harbour (including for sums in excess of £500k).

4.     Noted the Harbour Authority have been consulted and have ratified the proposals put forward by this report.