Chocolate Path River Wall Stabilisation

04/09/2018 - Chocolate Path River Wall Stabilisation

Cabinet:

 

1. Approved the spend for the remainder of the approved budget to undertake the (4.42m) full stabilisation works required for the complete extent of the Chocolate Path Wall.

 

2. Noted that the structural condition of the whole river wall continues to get worse and that there remains an urgent need for the full amount of funding sought (4.42m), for full repair and stabilisation of Chocolate Path throughout.

 

3. Delegated to the Executive Director Growth and Regeneration, in consultation with the Cabinet Member for Transport and Connectivity, the authority to procure contractors to carry out all works identified in Appendix A.