Issue details

Approval for scope changes to Temple Island enabling works project

Approval sought to de-scope EW2: Southern Access, £6.45m, from the initial cost profile and programme. It’s now partially replaced by the L and G scheme proposed masterplan which currently includes access from A4 to TI (subject to planning). An internal briefing note detailing the descope of Southern Access has been prepared and appended to this Form.
The funds for further RIBA design stages and Construction provisionally allocated will now be added to Contingency and to fund new scope items.
Approval sough to add new scopes:
EW6 River Wall scope will repair the man-made late 19th Century walls to preserve the structure and improve their aesthetics. The cost of repair work is estimated at £1.04m and subject to approval to use a proportion of the Contingency funding as a result of Decision 1.
EW7 provides for a haul road to be constructed in order to facilitate the construction works currently being undertaken by BCC, UoB and Network Rail. It is also likely to be used by the developer for their works in Phase 1. The cost of installation will be shared between the three parties with BCC’s contribution to install, maintain and reinstate equating to £220k. Approval is sought to meet this cost from the increased Continency funding pot.
Approval sought to fund three studies on the boundaries of Temple Island for £134K:
A4 Vehicle Protection study - £65K: BCC Highways have requested a study of the existing crash barrier and a design of solutions to reduce risk. Upon completion of this study, the project will come back to Delegated Authority to decide how BCC wish to undertake the remediation works.
Southern Gateway Ped/Cycle link Study - £29K: Feasibility study of additional infrastructure to run alongside the A4 between the Southern Access and SG Transport Hub.
Riverbank and Cliff Surveys – £40K: Required to investigate the condition of the boundary and the river edge protection.
Decisions on how to proceed with the outcomes of these studies will be sought separately, including the identification of funding sources.

Decision type: Non-key

Decision status: Recommendations Approved

Notice of proposed decision first published: 16/06/2021

Decision due: 15 Jun 2021 by Executive Director: Growth and Regeneration

Lead member: Marvin Rees, Mayor mayor@bristol.gov.uk

Contact: James Anderson, Head of Capital Projects Email: james.anderson@bristol.gov.uk.