08/06/2022 - Car Club ref: 1446    Recommendations Approved

As this is a direct award OED guidance states, decisions between £250k and £499,999k need to be approved by the Executive Director.

Decision Maker: Chief Executive

Decision published: 11/08/2022

Effective from: 08/06/2022

Decision:

Bristol City Council, Fleet Services have awarded its Car Club contract to the second and third highest ranked companies on the TPPL Framework, as the first ranked company was unable to meet BCC’s specification.
This purchase is being undertaken in accordance with Commercial Services Kent Limited (CSKL) and TPPL Vehicle Purchase Framework TPPLCSKL02.
The Procurement Partnership Ltd (TPPL) has completed a tendering exercise on behalf of Commercial Services Kent Limited (CSKL) to establish a Vehicle Car Club Framework covering Car Clubs and Pool Car schemes including travel management systems and packages.
A Procurement Officer has been appointed to this project and the process being followed by Fleet Services has been approved by the Procurement Team.

Lead officer: Nick Gingell


01/06/2022 - Contract award for provision of Domestic Abuse Services ref: 1397    Recommendations Approved

At a Cabinet meeting on 04/02/2020 authority to award the contract for domestic abuse services was delegated to the Executive Director, People in consultation with the Cabinet Member for Public Health and Communities.
At a further cabinet meeting on 09/03/2021 authority to award contracts to meet the requirements of the Domestic Abuse Act (Accommodation based domestic abuse support) was also delegated to the Executive Director for People in consultation with the Cabinet Member for Public Health and Communities.
Bristol City Council receives additional government funding from the Department of Levelling Up Housing and Communities (DLUHC) to enable it to meet these ‘new burdens’.
A compliant procurement process has taken place and Next Link’s tender submissions for both aspects of service provision were successful.

Decision Maker: Director: Communities & Public Health

Decision published: 13/06/2022

Effective from: 01/06/2022

Decision:

To award to Next Link the contract for the provision of:
1. Accommodation based domestic abuse support; and
2. Specialist domestic abuse services

Lead officer: Hugh Evans


30/05/2022 - Bristol Impact Fund 2021-2025: Award of Small Grants, Round One ref: 1392    Recommendations Approved

At its meeting on 25 February 2021, Cabinet approved the creation of the second Bristol Impact Fund (BIF) – Growing The Power of Communities, and authorised the Executive Director for People in consultation with Cabinet Member for Public Health and Communities to invite community and voluntary organisations to apply to Bristol Impact Fund and to award grants necessary for the implementation of Bristol Impact Fund Growing the Power of Communities for the period 1st October 2021 – 30th September 2025.
Within the overall BIF fund of £6.4m that Cabinet approved £300,000 is to be offered as two rounds of 18-month-long Small Grants of a maximum of £15,000 per grant. The Small Grants Fund is targeted at those communities experiencing the greatest inequality, defined as those areas of the city within the 20% most deprived within the Indices of Multiple Deprivation and equalities communities within the city.
This decision sets out the award of the first Small Grants round of £150,000.

Decision Maker: Director: Communities & Public Health

Decision published: 07/06/2022

Effective from: 30/05/2022

Decision:

To distribute £150,000 of Bristol Impact Fund Small Grants to 11 community and voluntary groups from 1st July 2022 to 31st December 2023.

Lead officer: Keith Houghton


07/06/2022 - Zero Emission Transport City ref: 1387    Recommendations Approved

To seek approval to accept a grant award from the Department of Transport (DfT) to commission and deliver feasibility and technical studies examining how the city can accelerate plans to decarbonise the transport network.

 

Decision Maker: Cabinet

Made at meeting: 07/06/2022 - Cabinet

Decision published: 07/06/2022

Effective from: 15/06/2022

Decision:

That Cabinet:

1. Approved the acceptance of the grant award of £500,000 from WECA utilising the DfT’s ZETC programme.

2. Authorised the Executive Director for Growth and Regeneration in consultation with the Cabinet Member for Transport and the Section 151 Officer to spend the funding including procuring and awarding the contract(s) necessary for investigating the activities listed in Appendix Aii in-line with the procurement routes and maximum budget envelopes outlined in this report, noting the associated Legal commentary.

3. Authorised Executive Director for Growth and Regeneration to invoke any subsequent extensions/variations specifically defined in the contract(s) being awarded, up to the maximum budget envelope outlined in this report.

4. Authorised the Head of Strategic Procurement & Supplier Relations to approve appropriate procurement routes to market where these are not yet fully defined in this report, or if changes to procurement routes are subsequently required.

 

Lead officer: Jacob Pryor


01/06/2022 - Half-hourly (large) Electricity Supply Contract ref: 1382    Recommendations Approved

Ensuring contracts are now in place for gas and two-thirds of electricity supplies.
The intent is that the larger electricity supplies (known as half-hourly or ‘HH’ supplies) would be provided through a sleeving arrangement, but it has not proven possible to secure bids for this through an open tender. A sleeving solution has been offered through a compliant Public Sector Buying Organisation framework, but will not be available until August 2022.
There is a clear and pressing need to maintain a compliant contract for power to supply council buildings, streetlights, and schools.
Failure to make arrangements before the current contracts expire on 31 May 2022 would mean the council pays off-contract rates until new contracts are in place. These rates are up to 100% more expensive.
It is therefore not financially viable to await for a key decision to be taken at the next cabinet meeting on 7 June 2022.

Decision Maker: Executive Director: Growth and Regeneration

Decision published: 07/06/2022

Effective from: 01/06/2022

Decision:

To extend the current electricity supply contract by a further two months to 31 July 2022, at an estimated cost of £1m.

Lead officer: Stephen Peacock


07/06/2022 - Microsoft Desktop Licensing – In-year Uplift and future contracting ref: 1393    Recommendations Approved

To seek approval to renew and increase the value of the existing contract and authority to procure and award a replacement contract from June 2023.

Decision Maker: Cabinet

Made at meeting: 07/06/2022 - Cabinet

Decision published: 07/06/2022

Effective from: 15/06/2022

Decision:

That Cabinet:

  1. Authorised the Director: Policy, Strategy and Digital in consultation with the Cabinet Member – Finance, Governance and Performance to take all steps required to incur the additional spend of up to £700,398 on the Bytes contract until May 2023 as outlined in this report, subject to this being contained within the Council’s overall revenue budget envelope.
  2. Authorised the Director – Policy, Strategy and Digital in consultation with the Deputy Mayor – Finance, Governance & Performance to take all steps required to procure and award a 3-year Microsoft Desktop Licensing contract, at a cost of up to £7m, with an approved Microsoft reseller, for the range of Microsoft products currently used by BCC, to include provision within the contract for products that support the BCC cloud migration and end-user computing strategy as outlined in this report.

 

Lead officer: Tim Borrett


07/06/2022 - 2021/22 Revenue Budget outturn ref: 1390    Recommendations Approved

To seek approval of the 2021/22 Revenue Budget Outturn.

 

Decision Maker: Cabinet

Made at meeting: 07/06/2022 - Cabinet

Decision published: 07/06/2022

Effective from: 15/06/2022

Decision:

That Cabinet noted:

  • The Council’s revenue outturn position of £0.9m underspend within the General Fund.
  • The Council’s outturn position of £4.4m underspend within the Housing Revenue Account to be carried forward within the HRA general reserve for the Council’s landlord functions.
  • The overspend of £14.6m and a total £24.6m carried forward deficit in the ring-fenced Dedicated Schools Grant Account (DSG).
  • A breakeven position on Public Health services.
  • The Council’s capital outturn position of £36.4m underspend against the revised Capital Programme Budget.
  • The in-year collection levels for Council Tax and Business Rates as set out in the report (see para 10 in Appendix A)
  • The level of aged debt as at 31 March 2022 (see para 11 in Appendix A)
  • The performance on delivery of savings as set out in Appendix A1.

 

That Cabinet Approved:

  • £0.2m be of the residual underspend being transferred to the Mayor’s office to reinstate the discretionary and non-staff related budget (for 2022/23 only) as agreed in the 2022/23 alternative budget amendment
  • £0.2m of the residual underspend to be used to replenish the Resources Operational Reserve as agreed in the 2022/23 alternative budget amendment
  • The remaining £0.5m of the residual underspend be transferred to the Council’s general reserve for consideration in subsequent years
  • That the revised financial reporting timetable as set out in Appendix 1b be agreed.

 

Lead officer: Denise Murray


07/06/2022 - Digital Strategy ref: 1391    Recommendations Approved

To seek approval of the refreshed digital strategy.

Decision Maker: Cabinet

Made at meeting: 07/06/2022 - Cabinet

Decision published: 07/06/2022

Effective from: 15/06/2022

Decision:

That Cabinet:

1. Approved the refreshed Digital Strategy for 2022-2027

2. Noted that a further report will come to Cabinet to approve the Digital Transformation Programme.

 

Lead officer: Tim Borrett


07/06/2022 - Council Tax Reduction Scheme 2023/24 ref: 1389    Recommendations Approved

To seek approval of the Council Tax Reduction Scheme 2023/24

Decision Maker: Cabinet

Made at meeting: 07/06/2022 - Cabinet

Decision published: 07/06/2022

Effective from: 15/06/2022

Decision:

That Cabinet:

1. Approved the Council Tax Reduction scheme 2023/24.

 

Lead officer: Matthew Kendall


07/06/2022 - Levelling Up Fund bid opportunities ref: 1388    Recommendations Approved

To seek approval of and delegate authority to submit identified schemes and Expressions of Interest for the Government’s Levelling Up Fund (LUF) second round.

 

Decision Maker: Cabinet

Made at meeting: 07/06/2022 - Cabinet

Decision published: 07/06/2022

Effective from: 15/06/2022

Decision:

That Cabinet:

1. Approved the submission of bids to the Levelling Up Fund for each of the two identified schemes, Filwood regeneration and Bristol Cycling Centre, as set out in this report.

2. Authorised, if successful, the Executive Director of Growth and Regeneration in consultation with the Cabinet Member for Finance and Cabinet Member for Housing Delivery and Homes, and S151 Officer, to accept and spend the funding including agreeing the terms of any grant award and procuring and awarding contracts (which may be over £500k) to deliver the relevant project, including design work and planning permission, within the maximum budget envelopes outlined within this report and without further reference to Cabinet.

3. Approved the allocation of local match funding [of 10%] from within the agreed HRA capital programme (Filwood) and Clean Air Zone (Cycling Centre) or other identified match options (subject to delegated authority limits).

4. Noted the previous Cabinet approval dated 18 January 2022 approving the use of the Housing General Fund towards the 10% match funding contribution as outlined in this report.

5. Authorised, if the bids are unsuccessful or fail to achieve the full ask, the Executive Director for Growth & Regeneration, in consultation with Cabinet Member for Finance and Cabinet Member for Housing, and S151 Officer to identify and submit bids for other potential sources of funding within the maximum budget envelopes outlined in this report.

 

Lead officer: Hannah French


07/06/2022 - Old City & King Street Pedestrianisation Scheme Full Business Case ref: 1386    Recommendations Approved

To authorise the approval and submission of the Full Business Case (FBC) for the Old City & King Street Pedestrianisation Scheme to the West of England Combined Authority (WECA).

 

Decision Maker: Cabinet

Made at meeting: 07/06/2022 - Cabinet

Decision published: 07/06/2022

Effective from: 15/06/2022

Decision:

That Cabinet:

1. Authorised the Executive Director, Growth and Regeneration, in consultation with the Cabinet Member for Transport and the S151 Officer to approve and submit the FBC for the Old City & King Street Pedestrianisation Scheme to WECA for funding of up to £2.5m, as outlined in this report.

2. Noted the submission of the OBC to WECA in April 2022 for approval in June 2022 and the development costs for the OBC to date of £344k.

3. Noted the total cost of £2.5m includes the development costs from OBC to FBC as outlined in this report.

4. Authorised, in the event that the bid is successful, the Executive Director for Growth and Regeneration, in consultation with the Cabinet Member for Transport and the S151 officer to take all steps required to procure and award all necessary contracts up to the value of £2.5 million (including any individual contracts over £500k) to deliver the schemes as outlined in this report.

5. Authorised Executive Director, Growth and Regeneration to invoke any subsequent extensions/variations specifically defined in the contract(s) being awarded, up to the maximum budget envelope outlined in this report.

6. Authorised the Head of Strategic Procurement & Supplier Relations to approve appropriate procurement routes to market where these are not yet fully defined in the report, or if changes to procurement routes are subsequently required.

 

 

 

Lead officer: Adam Crowther


07/06/2022 - Housing IT and Transformation programme – approval of Outline Business Case ref: 1396    Recommendations Approved

 

To seek approval of the Outline Business case to fund and deliver the Housing IT and Transformation programme including procuring and awarding contracts as required.

 

Decision Maker: Cabinet

Made at meeting: 07/06/2022 - Cabinet

Decision published: 07/06/2022

Effective from: 15/06/2022

Decision:

That Cabinet:

1. Approved the OBC for the Housing IT and Transformation Programme at Appendix A.

2. Authorised the Executive Director – Growth and Regeneration in consultation with the Cabinet Member for Housing Delivery and Homes to spend up to £1.39m, to deliver Phase Two of the programme including procuring and awarding contracts over £500k.

3. Noted: a report will be brought back to Cabinet for approval of the Full Business Case

Lead officer: Sarah Spicer


07/06/2022 - Safer Streets Fund Round 4 grant bid ref: 1383    Recommendations Approved

To note the submission of a bid and if successful, seek approval to accept and spend the funding awarded.

Decision Maker: Cabinet

Made at meeting: 07/06/2022 - Cabinet

Decision published: 07/06/2022

Effective from: 15/06/2022

Decision:

That Cabinet:

1. Noted the contents of the bid submitted to the Home Office for funding from the Safer Streets Fund Round 4 in Appendix A.

2. Authorised, if the bid is successful, the Executive Director, People (in consultation with the Cabinet Member for Public Health and Communities) to take all steps necessary to accept and spend the funding including procuring and awarding contracts (which may be over £500k) to implement the work as outlined in this report.

 

Lead officer: Clare Sims


07/06/2022 - Integrated Community Equipment Services (ICES) Award and Contract Extension ref: 1385    Recommendations Approved

To seek approval to award a new Integrated Community Equipment Services (ICES) contract from 1st October 2022 and to approve the extension of the existing contract from 1st July 2022 to commencement of new contract.

Decision Maker: Cabinet

Made at meeting: 07/06/2022 - Cabinet

Decision published: 07/06/2022

Effective from: 15/06/2022

Decision:

That Cabinet:

1. Authorised the Executive Director, People in consultation with the Cabinet Member for Adult Social Care and the CCG and Integrated Care System to award a new Integrated Community Equipment Services (ICES) contract to Medequip Assistive Technology Ltd from 1 October 2022 in line with the maximum budget envelopes outlined in this report.

2. Authorised the Executive Director, People to invoke any subsequent extensions/variations specifically defined in the contract(s) being awarded, up to the maximum budget envelope outlined in this report.

3. Noted the Officer Executive decision taken on May 10th to extend the current contract by 3 months to 30 June 2022 to allow for the extension request at Cabinet on June 7th 2022.

4. Authorised the Executive Director People in consultation with the Cabinet Member for Adult Social Care and the CCG and Integrated Care System to further extend the current contract up to the commencement of the new contract (planned for 1 October 2022) within the budget envelope of £381,000.

 

 

Lead officer: Lucia Dorrington


07/06/2022 - Extensions for Preventing Homelessness Accommodation Pathways – adults (22+) ref: 1395    Recommendations Approved

To seek approval to extend and vary the contracts.

 

Decision Maker: Cabinet

Made at meeting: 07/06/2022 - Cabinet

Decision published: 07/06/2022

Effective from: 15/06/2022

Decision:

That Cabinet:

1. Noted the previous approvals granted on 16th May 2017 and the contract details as outlined in this report and Appendix A.

2. Authorised the Executive Director Growth and Regeneration, in consultation with the Cabinet Member for Housing Delivery & Homes to:

(a) extend the following contracts, namely (i) Preventing Homelessness Accommodation Pathways – Men Only Services; (ii) Mix Accommodation; (iii) Women Only Services; (iv) Substance Misuse, each as summarised in Appendix A of this report, each for 1 + 1 years until 27th October 2024 with a maximum budget envelope of £5.273m p.a.

(b) extend the Preventing Homelessness Accommodation Pathway – Resettlement Service, as summarised in Appendix A of this report, for 1 year until 22nd October 2023 with a maximum budget envelope of £260k p.a.

 

Lead officer: Paul Sylvester


07/06/2022 - Expansion of the Climate and Ecological Emergency Catalyst Programme ref: 1394    Recommendations Approved

To seek approval to expand the existing Climate and Ecological Emergency Programme.

To note that Bristol has been accepted into the EU 100 Climate and Smart Cities Mission and to seek approval to join this initiative.

 

 

Decision Maker: Cabinet

Made at meeting: 07/06/2022 - Cabinet

Decision published: 07/06/2022

Effective from: 15/06/2022

Decision:

That Cabinet:

1. Approved expansion of the existing Climate and Ecological Emergency Programme to include additional projects and expenditure of an additional £905,000 to increase the council’s action to address the ecological emergency as outlined in this report and the Full Business Case.

2. Authorised the Executive Director of Growth and Regeneration, in consultation with the Cabinet Member for Climate, Ecology, Energy & Waste, the Cabinet Member for Finance, and the Section 151 Officer, to take all steps required to spend the additional £905k including authority to procure and award the contract(s) necessary to give effect to the decision, within the budget envelope.

3. Authorised the Executive Director of Growth and Regeneration, in consultation with the Cabinet Member for Climate, Ecology, Energy & Waste, the Cabinet Member for Finance, and the Section 151 Officer, to take all steps required to approve the extension or addition of new projects to the Climate and Ecological Emergency Programme and approve future spend (in accordance with the decision pathway) should further needs be identified and funds become available.

4. Noted that Bristol has been accepted into the EU 100 Climate and Smart Cities Mission and approve the City Council joining this initiative and integrating this into the Climate and Ecological Emergency Programme and its wider work to assist with achievement of the goals of the One City Climate Strategy.

 

 

Lead officer: Alex Minshull


07/06/2022 - Additional Provision Framework - Therapists, Mentors and Tutors Approved Provider List ref: 1378    Recommendations Approved

To approve the commissioning and establishment of a flexible framework of providers to deliver EHCP Additional Provision Services including therapies and learning support

Decision Maker: Cabinet

Made at meeting: 07/06/2022 - Cabinet

Decision published: 07/06/2022

Effective from: 15/06/2022

Decision:

That Cabinet:

1. Approved the establishment of a flexible framework for the purchasing of additional EHCP provision at a cost of up to £16.3million over 5 years.

2. Authorised the Executive Director, People in consultation with the Cabinet Member for Children’s Services, Education and Equalities to take all steps required to procure the flexible framework for the purchasing of additional EHCP provision (including the award of individual contracts to providers on the framework over £500k)

3. Authorised Executive Director, People in consultation with Cabinet Member for Children’s Services, Education and Equalities to extend or vary the framework contract(s) in-line with the procurement routes and maximum budget envelopes outlined in the report.

 

Wards affected: (All Wards);

Lead officer: Gail Rogers


07/06/2022 - Defra Innovation Resilience Programme Fund (Frome Catchment Innovation Programme) ref: 1384    Recommendations Approved

To seek approval to submit the Frome Catchment Innovation Programme Outline Business Case to the Environment Agency for technical assurance and financial approvals, and subsequently progress to Full Business Case and scheme delivery under delegated authority.

 

Decision Maker: Cabinet

Made at meeting: 07/06/2022 - Cabinet

Decision published: 07/06/2022

Effective from: 15/06/2022

Decision:

That Cabinet:

1. Approved submission of the Outline Business Case to the Environment Agency for technical assurance and financial approval of the Frome Catchment Innovation Programme as outlined in this report and Appendix A.

2. Authorised the Executive Director for Growth and Regeneration in consultation with the S151 officer and Cabinet Member for Finance, Governance and Performance to make an application for up to £7.3m grant funding to develop and deliver the programme of work identified within the Outline Business Case.

3. Authorised the Executive Director for Growth and Regeneration in consultation with the S151 officer and Cabinet Member for Finance, Governance and Performance, on successful grant award, to take all steps required to accept and spend the funding including entering into any agreements or procuring and awarding contracts (which may be over £500k) to deliver the programme of work identified in the Outline Business Case.

4. Authorised the Director – Economy of Place, in consultation with the partnership Directors Board and Cabinet Member for Strategic Planning, Resilience and Flood Strategy to proceed with the development and approval of FBC’s for individual work streams which may be over £500k.

5. Noted that officers will undertake public consultation in respect of options and detailed designs for individual work streams where relevant to inform a decision on scheme construction and delivery.

 

Lead officer: Adam Crowther


18/05/2022 - Permission to accept and spend the Prevent Priority fund grant from the Home Office ref: 1380    Recommendations Approved

Bristol City Council has made a successful bid for Home Office Prevent priority funding and has been awarded a grant of £126,231 for a period from April 2022 – March 2023. This grant will allow for the creation of two new posts – a Prevent Coordinator and a Prevent Education Officer. The funds also permit the Council to provide greater strategic oversight and an improved alignment with national Prevent objectives and practice. There is also funding for community engagement activity throughout this period. The provision with lead to an improved level of compliance with the Council’s statutory duty to Prevent as outlined above and will also in turn, serve to improve our safeguarding of vulnerable individuals through our Channel programme, our partnerships working and safety within our communities.

Decision Maker: Director: Children, Families & Safer Communities

Decision published: 31/05/2022

Effective from: 18/05/2022

Decision:

To accept the prevent Priority funds from the Home Office. Bristol City Council will use the funds to appoint two specialist Prevent posts, to provide strategic oversight and implement community engagement activities over a twelve-month period. The additional posts and community engagement funds will enable Bristol City Council to fulfil its statutory Prevent Duty under the Counter Terrorism and Security Act 2015 which requires all specified authorities to have “due regard to the need to prevent people from being drawn into terrorism”.

Lead officer: Clare Sims